Commissioning of equipment Adjust the pressure of safety valve on the gear pump: 1) 10MPa pressure gauge is connected to the pressure tap at the outlet of gear pump. 2) Loosen the safety valve of gear pump, and then block the pump outlet; 2) Start the motor and then adjust the pressure of safety...
Send Inquiry
Product Introduction

We continue to take the development idea of low cost and high efficiency, and our Scraper Bucket Rock Loader, Underground Mining Loader, Coal Mine Loader start to develop from low end to middle and high end. We are committed to complying with all relevant laws and regulations in our industry. Our team is experienced in managing complex regulatory and compliance issues.

Mucker Machine

Commissioning of equipment

Adjust the pressure of safety valve on the gear pump:

1) 10MPa pressure gauge is connected to the pressure tap at the outlet of gear pump.

2) Loosen the safety valve of gear pump, and then block the pump outlet;

2) Start the motor and then adjust the pressure of safety valve of gear pump to 10MPa for locking;

3) Remove the pressure gauge, cover the connector and connect the pipeline.

 Adjust the pressure of safety valve on the pilot oil line:

1) 10MPa pressure gauge is connected to the pressure tap at the pilot delivery valve.

2) The handle is pulled to the normal working position. The safety valve on pilot delivery valve is adjusted to 3.5MPa for locking;

3) Remove the pressure gauge, and cover the connector.

 

working mechanism:

 

120


 

 

 


We serve you with years of experience in the Lwl--180/75L Special Crawler Mucking Loader for Open Pit industry, and sincerely look forward to communicating and cooperating with you in a mutually beneficial and win-win manner. We're wanting ahead to forming successful enterprise relationships with new shoppers across the world during the in close proximity to long term. We strictly clarify work responsibilities and strengthen accountability, thus strengthening process control and strict quality management.